Differences over who should undertake a new feasibility study for the Gwanda solar project are delaying the signing of a revised contract between the Zimbabwe Power Company (ZPC) and contractors IntraTrek and Chint Electric Company. In July, Cabinet approved a revised implementation plan for the 100MW Gwanda solar PV project, in which the developers agreed to evacuate the first 10MW of the project to the national grid within six months of financial close, and brought in African Transmission Corporation (ATC) as transaction adviser for the project.