Algeria: GE/Metka to build gas power plant


Issue 255 - 31 May 2013 | 1 minute read

A consortium of GE International and Greek contractor Metka has signed an engineering, procurement and construction contract with Sonelgaz subsidiary Société Algérienne de Production de l’Electricité (SPE) to build an open-cycle gas-fired power plant in Hassi R’mel. The plant will have an available capacity of around 368MW and is expected to be finished within 30 months. The value of Metka’s portion of the contract is €93m ($120m), denominated in euros and Algerian dinars. The agreement is unrelated to GE’s delayed deal with Sonelgaz to supply 8,400MW of turbines.

Tagged with:

Pin Power

Pin Algeria

Want to read more?

Subscribe to African Energy

View subscription options

This article is available to registered users

Login

Don't have an account?

Register for access to our free content

An account also allows you to view selected free articles, set up news alerts, search our African Energy Live Data power projects database and view project locations on our interactive map

Register