Zambia: Maamba first unit synchronised


Issue 329 - 05 Aug 2016 | 1 minute read

Nava Bharat Ventures announced in late July that Maamba Collieries has synchronised the first 150MW unit of a coal power plant to the grid. The much-needed power has come later than planned, with Zambia purchasing power from emergency power plants and the Southern African Power Pool in the interim as hydropower plants have suffered from drought and poor management. Nava Bharat said that “the synchronisation of the second 150MW unit will follow soon while stabilisation and commercial operations of the two units will be pursued in the coming weeks”.

Tagged with:

Pin Power

Pin Zambia

Want to read more?

Subscribe to African Energy

View subscription options

This article is available to registered users

Login

Don't have an account?

Register for access to our free content

An account also allows you to view selected free articles, set up news alerts, search our African Energy Live Data power projects database and view project locations on our interactive map

Register