Ghana: Jubilee production below target
Issue 270
- 30 Jan 2014
| 1 minute read
Tullow Oil continues to face problems in increasing oil production from the Jubilee field. An operational update on 15 January said output averaged 100,000 b/d for 2013, lower than the planned 120,000 b/d, following issues with the water injection system on the floating production, storage and offloading (FPSO) vessel that Tullow said had now been resolved. However, increasing output to the target of 120,000 b/d is hampered by difficulties with handling the associated gas. Tullow said the Ghana National Gas Company’s onshore gas-processing plant would not be ready to receive Jubilee gas until H2 2014.