385

New petroleum, energy and renewable energy minister Abdourahmane Cissé’s approval of plans for Paris-based investment company Eranove Group to build a 390MW gas-fired power plant at Jacqueville, near Abidjan, and for Globeleq’s 430MW Azito plant to add another 253MW in a CFA225.8bn ($385m) revamp suggests an acceleration of efforts to have 4GW of installed capacity in place by the time Côte d’Ivoire goes to the polls in 2020.