Société d’Energie et d’Eau du Gabon (SEEG) is rehabilitating the 5MW Bongolo hydropower plant in Ngounié province with the aim of restoring its installed capacity and improving supply in the region. The project, which will cost nearly CFAF7bn ($12.7m) to be financed entirely by the utility, will entail replacing the plant’s five turbines, including automation and control systems, as well as the complete upgrading of units G1 and G2 and all hydro-mechanical structures.